Estimates and Deadlines

A number said in passing often turns into a commitment. Imagine your PM asks between meetings how long the checkout redesign will take, and you say two weeks because the talk is already moving on.

Learn on the move: press play and turn your commute, walk or drive into time that grows your design career.

· Updated November 2026 · Reviewed by Olesia Borysova, lead product designer
Share
Share

That number then travels into a sprint plan, a roadmap and maybe a promise to a customer. None of those places record that it was a guess made in a corridor. Estimating has methods, and fixed dates have answers of their own.

Where Estimates and Dates Meet

Most estimate trouble in a product team shows up at four points, and each one has its own tool:

  • Size inside the team: story points and planning poker, sized against work the team already finished.
  • Design effort: the activities, a range with the likely case marked and the assumptions behind it.
  • A fixed date: a check of whether the date is real, and a cut list for what fits.
  • New scope on the same date: two options and a recommendation.

So the work here stops at effort and dates. Turning effort into a price and a contract is a separate skill, taught in Proposals, Pricing & Contracts.

Points & Planning Poker

Imagine a sprint report where your team finished 24 points and the team next door finished 40. A manager asks why your team is slower, and nobody in the room can answer in one sentence.

That's because a story point only means something inside the team that agreed it. Points, planning poker and velocity help one team plan its next sprint, and each of them breaks once it leaves that team.

What a Story Point Measures

A story point is a unit of relative size. It combines how much work an item holds, how complex it is and how much about it is still unknown. An item sized at 4 points is about twice an item sized at 2, for the team that sized both. Here is what goes into one story point:

What a story point combines: how much work, how complex and how much is unknown, for ORD-51, export orders as CSV, sized at 4. A finished item, print a single order, sits at 2, about half the size.

That relative scale grew out of time estimates. Ron Jeffries recalls that his early Extreme Programming team estimated in "ideal days" and multiplied them by a load factor of about three. Ideal days were then renamed points, so stakeholders would stop reading them as calendar days.

So the point leans on comparison, which people handle better than duration. Asking whether an item is bigger than the profile page shipped last month gives everyone the same piece of work to argue from.

The Deck and the Reference Story

Planning poker gives every person a deck of cards with a fixed set of sizes. James Grenning described the game in April 2002, in a paper subtitled "How to avoid analysis paralysis while release planning." His deck held 1, 2, 3, 5, 7, 10 and an infinity card for work too big to size.

Later decks kept the idea and changed the numbers. Mike Cohn's deck at Mountain Goat Software runs 0, 1, 2, 3, 5, 8, 13, 20, 40 and 100. In Agile Estimating and Planning (2005), Cohn explains that the gaps widen because larger items carry more uncertainty. Here are both decks, with a reference story under them:

Planning poker decks: James Grenning's 2002 deck with 1, 2, 3, 5, 7, 10 and infinity, the Mountain Goat Software deck from 0 to 100, and a reference story, the password reset flow, sized at 3.

That's why a team also keeps two or three reference stories. A reference story is a finished item everybody remembers, pinned at a known size, such as "the password reset flow was a 3". New work gets sized against it, so the scale stays tied to real work.

How a Round Runs

A round of planning poker follows the same steps for every item:

  • The product owner reads the item and answers questions about it.
  • Everyone picks a card in private.
  • All cards turn over at once.
  • The people with the highest and lowest cards explain their reasoning.
  • The team votes again until the cards sit close together.

The private pick is what makes the game work. Without it, the first number spoken anchors the room, an effect Amos Tversky and Daniel Kahneman described in 1974. The most senior voice then sets the size of work they may never touch.

That's also why the gap between a 3 and a 13 is worth more than the final number. Imagine the designer plays 13 on a "simple" search filter because its empty state, errors and mobile layout are unscoped. That talk surfaces the missing parts before anybody builds them. Here is one round for that search filter, from the private pick to the re-vote:

A planning poker round for ORD-42, filter orders by status. Five people pick in private, then reveal 3, 3, 5, 3 and 13. An engineer says the filter API already exists, the designer says the empty state, errors and mobile layout are unscoped, and the re-vote settles on 8.

Velocity as a Capacity Number

Velocity is the number of points a team finishes in a sprint. It exists for planning, so a team that finished 21, 24 and 23 points in its last three sprints can take in about 22 next time. The figure belongs to that team alone.

That's why comparing velocity between teams produces a number with no meaning, since their points are different units. Jeffries writes that "comparing teams on quality of estimates or velocity is harmful." Once velocity becomes a score, estimates grow, the chart rises and the same amount of work ships.

That pattern is Goodhart's law, which Marilyn Strathern put in its best-known form in 1997: "When a measure becomes a target, it ceases to be a good measure." Here is velocity used both ways:

Wrong: a sprint report ranking teams by points finished, Search 40, Orders 24, Account 19. Right: the Orders team's own velocity of 21, 24 and 23 points, used to plan about 22 for the next sprint.

When Points Are the Wrong Tool

Points suit a steady stream of similar delivery work, and the Scrum Guide 2020 never asks for them. It leaves sizing to the developers and names burn-downs, burn-ups and cumulative flow as ways to forecast. Jeffries now suggests counting finished stories and forecasting from that rate.

In practice that means picking the unit for the audience. For a question nobody can size yet, a spike with a fixed timebox is more honest than a card. For a stakeholder outside the team, a range in days is the number they can act on.

Here is the same estimate given to a stakeholder in points and in days:

A sales lead asks when customers can filter orders by status. Wrong: the PM answers that it is an 8. Right: the PM answers between 6 and 9 working days once work starts, most likely 7.

Pro tip: Open every planning session with the reference stories, their sizes and links to the shipped work. A new teammate can then size their first item against something they can open.